The Electricity Act Article 18
The Electricity Transmission and Distribution Enterprise shall not refuse any request put forward by any Electricity-Generating Enterprise or operator of Self-Use Power-Generation Equipment for connection to its power grid. Renewable Energy-Based Electricity Generating Enterprise shall be given priority in grid connections. However, this Article does not apply to Electricity Facilities or Self-Use Power-Generation Equipment that request connection but do not meet the requirements provided in paragraphs 1 and 3 of Article 25, Article 26, Article 29 to Article 31, Article 71 mutatis mutandis applying the above provisions, or Article 32.