Regulations for the Implementation of Procurement on a Turnkey Basis Article 8

For procurement on a turnkey basis, an entity shall prescribe in the tender documentation the following:1.the winning supplier shall submit its design to the entity or any institution designated by it for approval prior to the commencement of construction, supply or installation;2.where a change of design is necessary, an approval of the entity shall be obtained or that the matter shall be handled in a manner as notified by the entity. In the event that such change is not attributable to the supplier , the supplier may request the entity to reimburse any necessary additional expenses incurred by it in fulfilling the contract; and3.where the design failed to meet the requirements set out in the contract or that the supplier is unable to change such design in a manner as notified by the entity, the entity may terminate or rescind the contract.
中文原文 統包實施辦法第8條
機關以統包辦理招標,應於招標文件規定下列事項:
一、得標廠商之設計應送機關或其指定機構審查後,始得據以施工或供應、安裝。
二、設計有變更之必要者,應經機關同意或依機關之通知辦理。
其變更係不可歸責於廠商者,廠商得向機關請求償付履約所增加之必要費用。
三、設計結果不符合契約規定或無法依機關之通知變更者,機關得終止或解除契約。

English translation for reference only; the Chinese text prevails. Not legal advice.