Enforcement Rules of the Government Procurement Act Article 92

A construction contractor shall notify the construction supervision unit and the entity in writing of the date of completion prior to or on the date of completion. Unless otherwise specified in the contract, the entity shall, accompanied by the supervision unit and the contractor and within 7 days from the date of receipt of the written notification, check the completed items and quantities with the requirements specified in the contract, drawings or samples to ascertain that the construction work is completed. The entity may still ascertain completion of the construction work in case that the representative of the contractor is not present in the inspection event.After completion of construction work, the supervision unit shall, within 7 days after completion of the construction work, provide the drawings, detailed list of settlement, and other data required by the contract to the entity for reviewing, except otherwise specified in the contact. Where there is a preliminary inspection procedure, the entity shall conduct the preliminary inspection and make a record within 30 days from the date of receipt of all of the foregoing data.The preceding two paragraphs shall apply mutatis mutandis to the procurement of properties and services where a preliminary inspection is adopted.
中文原文 政府採購法施行細則第92條
廠商應於工程預定竣工日前或竣工當日,將竣工日期書面通知監造單位及機關。
除契約另有規定者外,機關應於收到該書面通知之日起七日內會同監造單位及廠商,依據契約、圖說或貨樣核對竣工之項目及數量,確定是否竣工;廠商未依機關通知派代表參加者,仍得予確定。
工程竣工後,除契約另有規定者外,監造單位應於竣工後七日內,將竣工圖表、工程結算明細表及契約規定之其他資料,送請機關審核。
有初驗程序者,機關應於收受全部資料之日起三十日內辦理初驗,並作成初驗紀錄。
財物或勞務採購有初驗程序者,準用前二項規定。

English translation for reference only; the Chinese text prevails. Not legal advice.