Enforcement Rules of the Government Procurement Act Article 104-1
The dates of submission of a protest and a complaint depend on the date on which the protest is filed with the procuring entity and the date on which the complaint is filed with the Complaint Review Board for Government Procurement (CRBGP), respectively.In the event that the supplier files its protest or complaint to a wrong entity, the date on which such protest or complaint is filed with the wrong entity shall be deemed as the date of receipt of the protest or complaint.
中文原文 政府採購法施行細則第104-1條
異議及申訴之提起,分別以受理異議之招標機關及受理申訴之採購申訴審議委員會收受書狀之日期為準。
廠商誤向非管轄之機關提出異議或申訴者,以該機關收受之日,視為提起之日。