Government Procurement Act Article 70-1

In conducting planning or design of a construction work, an entity shall analyze the potential construction hazards depending on the construction scale and characteristics, prepare the drawings and specifications related to safety and health in accordance with the Occupational Safety and Health Act and its regulations, and quantify the expenditures of safety and health thereof. In conducting a procurement of construction work, an entity shall include in the tender documentation the design results of the preceding paragraph, and the requirements of the supplier to arrange or take necessary preventive equipments or measures according to the Occupational Safety and Health Act and relevant regulations, and implement management and training concerning safety and health to prevent occupational accidents of workers and ensure the safety of construction. Where an occupational accident occurs in the construction site due to lack of required equipments or facilities related to safety and health or poor of them against the related regulations or contract, the supplier shall not only be punished pursuant to the Occupational Safety and Health Act and its regulations, but also be dealt with according to this Act and the requirements of a contract.
中文原文 政府採購法第70-1條
機關辦理工程規劃、設計,應依工程規模及特性,分析潛在施工危險,編製符合職業安全衛生法規之安全衛生圖說及規範,並量化編列安全衛生費用。
機關辦理工程採購,應將前項設計成果納入招標文件,並於招標文件規定廠商須依職業安全衛生法規,採取必要之預防設備或措施,實施安全衛生管理及訓練,使勞工免於發生職業災害,以確保施工安全。
廠商施工場所依法令或契約應有之安全衛生設施欠缺或不良,致發生職業災害者,除應受職業安全衛生相關法令處罰外,機關應依本法及契約規定處置。

English translation for reference only; the Chinese text prevails. Not legal advice.