Regulations for Bid Bond, Guarantee Bond and Other Guarantees Article 17

Where a tenderer deposits a performance bond in the form of an irrevocable standby letter of credit issued or confirmed by a bank, bank’s written joint and several guarantee or insurer’s insurance policy of joint and several guarantee, unless otherwise prescribed by the tender documentation, the validity period of such instruments shall be 90 days longer than the time-limit for final construction, supply or installation prescribed in the contract.Where a supplier fails to perform the contract within the time-limit prescribed in the contract, or that inspection and acceptance may not be accomplished within the validity period referred to in the preceding paragraph due to causes attributable to the supplier, the validity period of performance bond shall be extended according to the duration of such delay.
中文原文 押標金保證金暨其他擔保作業辦法第17條
廠商以銀行開發或保兌之不可撤銷擔保信用狀、銀行之書面連帶保證或保險公司之保證保險單繳納履約保證金者,除招標文件另有規定外,其有效期應較契約規定之最後施工、供應或安裝期限長九十日。
廠商未能依契約規定期限履約或因可歸責於廠商之事由致無法於前項有效期內完成驗收者,履約保證金之有效期應按遲延期間延長之。

English translation for reference only; the Chinese text prevails. Not legal advice.