Enforcement Rules of Act for Promotion of Private Participation in Infrastructure Projects Article 83
When the authority in charge suspends a part or all of the construction or the operation of the private institution in accordance with Subparagraph 2, Paragraph 1, Article 52 of the Act, the authority in charge shall notify the private institution of the following matters in writing:1. The specific fact that the private institution has made no improvement within the time limit or that the improvement is ineffective;2. The suspension date of the construction or operation;3. The scope of the suspended construction or operation;4. The items, the standard and time limit still requiring improvement after the suspension of the construction or operation; and5. The consequences of failing to complete the improvement within the time limit.The authority in charge may, depending on the defects in the construction and the relevancy to other construction and within the limitation of the least influence on the total construction, quality and the progress, determine the scope of the construction to be suspended as specified in Subparagraph 3 of the preceding paragraph. The authority in charge may determine the scope of the business operation to be suspended based on the objective facts and within the necessary scope to improve the defects.
中文原文 促進民間參與公共建設法施行細則第83條
主辦機關依本法第五十二條第一項第二款規定中止民間機構興建或營運一部或全部時,應以書面載明下列事項,通知民間機構:
一、屆期不改善或改善無效之具體事實。
二、中止興建或營運之日期。
三、中止興建之工程範圍或中止營運之業務範圍。
四、中止興建或營運後,應繼續改善之項目、標準及期限。
五、屆期未完成改善之處理。
前項第三款中止興建之工程範圍,得由主辦機關視該工程之缺失及與其他工程之相關性,於影響整體工程興建、品質及進度最少之範圍內決定之;中止營運之業務範圍,由主辦機關依客觀事實,在改善缺失必要之範圍內決定之。
一、屆期不改善或改善無效之具體事實。
二、中止興建或營運之日期。
三、中止興建之工程範圍或中止營運之業務範圍。
四、中止興建或營運後,應繼續改善之項目、標準及期限。
五、屆期未完成改善之處理。
前項第三款中止興建之工程範圍,得由主辦機關視該工程之缺失及與其他工程之相關性,於影響整體工程興建、品質及進度最少之範圍內決定之;中止營運之業務範圍,由主辦機關依客觀事實,在改善缺失必要之範圍內決定之。