Enforcement Rules of Act for Promotion of Private Participation in Infrastructure Projects Article 78
Serious delay in work schedule as specified in Paragraph 1, Article 52 and Paragraph 1, Article 53 of the Act shall mean failure to complete the construction within the time limit stipulated in the concession agreement; or the percentage of construction work falling behind a certain level as stipulated in the concession agreement. Major defects in quality of the construction work shall mean the construction work violates the law and regulations or the construction standards set in the concession agreement; or the institution agreed upon by both the authority in charge and the private institution determines that the construction work seriously impairs the quality of public construction. Poor operation shall mean the private institution violates the law and regulations or the concession agreement in aspects of public safety, service quality or relevant administration during the operation period, which will affect the operation and is a serious violation.