Enforcement Rules of Act for Promotion of Private Participation in Infrastructure Projects Article 67

The authority in charge should set reasonable deadlines for contract negotiation and execution, depending on the character of the infrastructure project.Unless under special circumstances, the deadlines for contract negotiation and execution specified in the preceding paragraph shall be no later than the timeframe set in the following clauses:1. For contract negotiation: The period between the day the authority in charge notifies the best applicant to start contract negotiation and the day the negotiation is completed shall be no longer than twice the period of application, with a ceiling of six months; and2. For contract execution: The period between the day the negotiation is completed and the day the contract is executed shall be limited to one month, with possible extension of another one month. However, the period before execution, specified in Paragraphs 1 and 2, Article 45 of the Act as preparation and correction time, shall be excluded.The authority in charge is forbidden to delegate its subordinate entities or commission other entities (institutions) to conduct the determination of the special circumstances specified in the preceding Paragraph.
中文原文 促進民間參與公共建設法施行細則第67條
主辦機關應視公共建設性質,訂定合理之議約及簽約期限。
前項議約及簽約期限,除有特殊情形者外,不得逾下列期限:
一、議約期限:自主辦機關通知最優申請人開始議約之日起至完成議約止之期間,不得超過申請期間之二倍,且以六個月為限。
二、簽約期限:自議約完成至簽訂契約期間,以一個月為原則,並得展延一個月。
但簽約前依本法第四十五條第一項及第二項規定之籌辦及補正時間,不予計算。
前項特殊情形之認定,不得授權所屬或委託其他機關(構)執行之。

English translation for reference only; the Chinese text prevails. Not legal advice.