Enforcement Rules of Act for Promotion of Private Participation in Infrastructure Projects Article 45
When requesting the competent authority of zone/section expropriation to carry out the expropriation operation in accordance with Article 19 of the Act, the authority in charge shall prepare a development plan in advance for the approval of the Executive Yuan.The development plan specified in the preceding Paragraph shall include the following items:1. The character of the infrastructure project and the relationship to the relevant superior plan;2. The goal of the development;3. The scope of the intended development area;4. Major public facilities;5. Current status of the development areas and neighboring areas;6. The conception of the whole development;7. The means of development by one's own or by commissioning others;8. The intended proportion of the land for compensation;9. The plan for building demolition and inhabitant relocation;10. Development schedule;11. Land use plan;12. Financial analysis and plan;13. Coordination measures;14. Allocation of responsibilities;15. Prospective effects; and16. Other items that should be specified.If the cost of other public facilities as specified in the latter part of Paragraph 2, Article 46 of the Act is to be included in the financial analysis and plan specified in Subparagraph 12 of the preceding paragraph, the cost may be added to the ceiling amount of the total expenses for zone/section expropriation and development specified in Subparagraph 3, Paragraph 2, Article 19 of the Act. The condition should be stated in the development plan and the tender announcement for the participation of the private institutions.After the development plan is approved by the Executive Yuan, the authority in charge shall prepare the relevant blueprints of the cadastral map, the scope map, the current development situation of the areas neighboring the site, the urban planning map or zoning map for the use of non-urban land, and the land designation map; evaluate and define the scope of the land to be expropriated by zone or section on site in conjunction with the authorities in charge of zone/section expropriation, urban planning, land administration, environmental protection, and transportation; and then request the competent authority of zone/section expropriation to carry out the expropriation operation in accordance with the applicable laws.If the development plan needs to be adjusted to comply with the decisions of the Urban Planning Commission or the Land Expropriation Review Panel of the Ministry of Interior, the authority in charge shall amend the development plan and submit the revised plan to the Executive Yuan for approval.
中文原文 促進民間參與公共建設法施行細則第45條
主辦機關依本法第十九條規定洽請區段徵收主管機關辦理區段徵收者,應事先擬定開發計畫,報請行政院核定。
前項開發計畫,應載明下列事項:
一、該公共建設事業計畫之特性及與相關上位計畫之關係。
二、開發目標。
三、預定開發地區範圍。
四、主要公共設施項目。
五、開發地區及鄰近地區發展現況。
六、整體發展構想。
七、自行或委託辦理之開發方式。
八、預定抵價地比例。
九、拆遷安置構想。
十、開發進度。
十一、土地使用計畫。
十二、財務分析及計畫。
十三、配合措施。
十四、責任分工。
十五、預期效益。
十六、其他應載明事項。
前項第十二款財務分析及計畫,如將第四十六條第二項後段之其他公共設施費用計入者,其得計入本法第十九條第二項第三款區段徵收開發總成本之額度上限,應於開發計畫中敘明,並應納入徵求民間參與公告內容。
開發計畫報請行政院核定後,主辦機關應備齊相關之地籍藍曬圖、範圍圖、基地附近地區發展現況資料、都市計畫圖或非都市土地使用分區圖及用地編定圖等,會同區段徵收主管機關及都市計畫、地政、環境保護、交通等有關機關,現場評估勘定區段徵收之範圍後,洽請區段徵收主管機關依法辦理區段徵收。
開發計畫因配合都市計畫委員會或內政部土地徵收審議小組審議調整者,主辦機關應修正開發計畫,報請行政院備查。
前項開發計畫,應載明下列事項:
一、該公共建設事業計畫之特性及與相關上位計畫之關係。
二、開發目標。
三、預定開發地區範圍。
四、主要公共設施項目。
五、開發地區及鄰近地區發展現況。
六、整體發展構想。
七、自行或委託辦理之開發方式。
八、預定抵價地比例。
九、拆遷安置構想。
十、開發進度。
十一、土地使用計畫。
十二、財務分析及計畫。
十三、配合措施。
十四、責任分工。
十五、預期效益。
十六、其他應載明事項。
前項第十二款財務分析及計畫,如將第四十六條第二項後段之其他公共設施費用計入者,其得計入本法第十九條第二項第三款區段徵收開發總成本之額度上限,應於開發計畫中敘明,並應納入徵求民間參與公告內容。
開發計畫報請行政院核定後,主辦機關應備齊相關之地籍藍曬圖、範圍圖、基地附近地區發展現況資料、都市計畫圖或非都市土地使用分區圖及用地編定圖等,會同區段徵收主管機關及都市計畫、地政、環境保護、交通等有關機關,現場評估勘定區段徵收之範圍後,洽請區段徵收主管機關依法辦理區段徵收。
開發計畫因配合都市計畫委員會或內政部土地徵收審議小組審議調整者,主辦機關應修正開發計畫,報請行政院備查。