Regulations Governing the Planning, Appraisal, Implementation, Supervision and Performance Evaluation of International Cooperation and Development Affairs Article 5

When implementing development projects, the competent authority or other government agencies/institutions shall carry out regular supervision of such projects with partner countries to ensure alignment between the implementation results and project objectives.Within six months after the completion of a development project, the competent authority or other government agencies/institutions shall work with partner countries to determine whether project effectiveness was achieved and prepare a project completion report. Any project completion report prepared by other government agencies/institutions shall be submitted to the competent authority for reference.The causes of failure to achieve project objectives shall be clearly stated in the project completion report for reference when formulating future development projects.
中文原文 國際合作發展事務規劃評估執行監督及績效考核辦法第5條
發展計畫執行期間,主管機關或其他政府機關(構)應定期與合作國家計畫執行機關(構)共同辦理計畫監督,以確保計畫執行成效與計畫目標之一致性。
發展計畫執行完畢後六個月內,主管機關或其他政府機關(構)應彙整其與合作國家就計畫成效是否達成計畫目標之自我評估情形,作成計畫結案報告。
由其他政府機關(構)作成之計畫結案報告,應送主管機關備查。
前項計畫結案報告,如有未達成計畫目標之情形者,應敘明原因,並作為未來擬訂相關發展計畫之參考。

English translation for reference only; the Chinese text prevails. Not legal advice.