Enforcement Rules for the New Town Development Act Article 29
The “factors not attributable to the landownership holder” as mentioned in Paragraph 2, Article 18 of the Act include the following situations:Failure to start construction as scheduled or delay of completion caused by serious natural disaster. Failure to start construction as scheduled or delay of completion caused by occurrence of war or great social, or economic incidence. Delay of commencement or completion for matching with other important national or local construction projects. Failure to start construction within specified time limit due to delay in examination of urban design or building permit.
中文原文 新市鎮開發條例施行細則第29條
本條例第十八條第二項所定不可歸責於土地所有權人之事由,包括下列情形:
一、遭逢天然重大災害,致無法如期開工或延誤完工時程者。
二、遭逢戰爭、或社會、經濟之重大變故,致無法如期開工或延誤完工時程者。
三、因配合國家或地方其他重大建設需要,致須延後開工或延長完工時程者。
四、因都市設計或建築執照審查延宕,致無法於規定期限內開工者。