New Town Development Act Article 5
After the feasibility study report (drawing) is approved, the central authority shall give 30-day announcement, and upon expiration of the announcement period, shall immediately set out to or designate the municipal or county (city) authority to perform layout and design of the new town, and make the special district plan of the new town as the reference for development of new towns.During the above-mentioned announcement public period, public hearing shall be held. Where more than half of the private land owners, who possess more than half of the private lands in the specific zone, bring forward objection, the central competent authority shall perform mediation and arbitration, modify or abolish the feasibility study report with consideration of the reasons of objection and the conclusion of public hearing, and submit the report again for review, and then deal with the case according to the result of review.Where the lands of preserved area within the planned zone for new town are not developed within 20 years, the authority shall cooperate with the new town development to carry out purchase or requisition, or permit other persons or organization to develop the lands.
中文原文 新市鎮開發條例第5條
中央主管機關於可行性規劃報告書(圖)核定後,應公告三十日,公告期滿,應即進行或指定直轄市、縣(市)主管機關進行新市鎮之規劃與設計,擬定新市鎮特定區計畫,作為新市鎮開發之依據。
前項公告期間內應舉辦公聽會,特定區內私有土地所有權人半數以上,而其所有土地面積超過特定區私有土地面積半數者,表示反對時,中央主管機關應予調處,並參酌反對理由及公聽會之結論,修訂或廢止可行性規劃報告,重行報核,並依其核定結果辦理之。
新市鎮計畫範圍內之保護區土地,如逾二十年未開發使用者,主管機關應併同新市鎮開發辦理協議價購、區段徵收,或許可私人或團體申請開發。
前項公告期間內應舉辦公聽會,特定區內私有土地所有權人半數以上,而其所有土地面積超過特定區私有土地面積半數者,表示反對時,中央主管機關應予調處,並參酌反對理由及公聽會之結論,修訂或廢止可行性規劃報告,重行報核,並依其核定結果辦理之。
新市鎮計畫範圍內之保護區土地,如逾二十年未開發使用者,主管機關應併同新市鎮開發辦理協議價購、區段徵收,或許可私人或團體申請開發。