Regulations on Use Control of Lands and Buildings within New Town Special Areas Before Implementation of Overall Development English Translation Form Article 6

After the plan of extension is approved by the central authority of the objective undertaking, the factories legally registered before the plan of new town special areas is issued and enforced may apply for extension of temporary factory buildings within the lands presently owned by the factory or by adjacent land.The above-mentioned lands presently owned by the factory are limited to the lands that have been possessed by the factory before the plan of new town special district is issued and enforced;The adjacent land for the application for additional temporary building shall not exceed twice the total area of the existing factory and application shall be limited of one time.The additional temporary building coverage ratio of new and old buildings may not exceed 70% and the Volume ratio may not exceed 210%,the construction of the buildings shall be limited to made of wood & bamboo, brick, or metal structure.
中文原文 新市鎮特定區實施整體開發前區內土地及建築物使用管制辦法第6條
新市鎮特定區計畫發布實施前,經合法登記之工廠,得以其既有廠地及毗鄰土地申請增建臨時廠房,並於增建完成後送請工業主管機關變更登記。
前項既有廠地,以該工廠於新市鎮特定區計畫發布實施前即已存在者為限;申請增建臨時廠房之毗鄰土地,其面積不得超過既有廠地總面積之二倍,並以申請一次為限。
申請增建之臨時廠房,其建蔽率新舊合計不得超過百分之七十,容積率不得超過百分之二百十。
建築之構造以磚造、加強磚造、金屬架構式構造、鋼構造等建築物為限。

English translation for reference only; the Chinese text prevails. Not legal advice.