Spatial Planning Act Article 29

After receiving a land use permit from the competent authority, each applicant shall undertake the following before beginning to use the land according to the approved plan.1.Delineate areas to be registered as for public facilities and belonging to the municipality or county (city) or township (town, city, district) and transfer the ownership of such areas to the municipality or county (city) government or township (town, city).2.Pay the environmental conservation fee to the central competent authority and the impact fee to the competent authority of the municipality or county (city).3.Change the land for designated use according to the land use plan.Public facilities shall be completed in stages according to the land use plan and must pass inspections before the applicant can obtain use permits for these facilities; the applicant must also register such facilities as the property of the municipality or county or township (town. city) before the competent authority may issue use permits for buildings in areas that are not for public facilities. However, applicants who have offered to provide services in place public facilities and have obtained the consent of the competent authorities of municipality or county (city) or the building authority, are excluded.Article 25 of the Land Act shall not apply when an applicant constructs public facilities in the land for public facilities, as stated in the preceding paragraph.The central competent authority shall establish regulations regarding the procedure to be followed after applicants have been given permission to use the land, the means of operation, the undertakings, public facility items and related matters.If relevant provisions in other regulations apply, then the registration of ownership of the land for public facilities and of the facilities thereon, as stated in Paragraphs 1 and 2, shall be conducted accordingly. If the ownership is to be transferred to the municipality or county (city) or township (town, city), then the applicant may register such transfers by presenting the permission documents that are specified in Article 27. The registering agency need not issue an ownership certificate when processing such a transfer of registration but is required to notify the relevant municipality or county (city) government or township (town, city) office after the registration has been completed.
中文原文 國土計畫法第29條
申請人於主管機關核發使用許可後,應先完成下列事項,始得依經許可之使用計畫進行後續使用:
一、將使用計畫範圍內應登記為直轄市、縣(市)或鄉(鎮、市)管有之公共設施用地完成分割、移轉登記為各該直轄市、縣(市)或鄉(鎮、市)有。
二、分別向中央主管機關繳交國土保育費及直轄市、縣(市)主管機關繳交影響費。
三、使用地依使用計畫內容申請變更。
前項公共設施用地上需興建之設施,應由申請人依使用計畫分期興建完竣勘驗合格,領得使用執照並將所有權移轉登記為直轄市、縣(市)或鄉(鎮、市)有後,其餘非公共設施用地上建築物始得核發使用執照。
但經申請人提出各分期應興建完竣設施完成前之服務功能替代方案,並經直轄市、縣(市)或特設主管建築機關同意者,不在此限。
申請人於前項公共設施用地上興建公共設施時,不適用土地法第二十五條規定。
第一項及第二項許可使用後之程序、作業方式、負擔、公共設施項目及其他相關事項之辦法,由中央主管機關定之。
第一項及第二項之公共設施用地及設施,其所有權移轉登記承受人依其他法律另有規定者,從其規定;申請移轉登記為直轄市、縣(市)或鄉(鎮、市)有時,得由申請人憑第二十七條第一項規定許可文件單獨申請登記;登記機關辦理該移轉登記時,免繕發權利書狀,登記完畢後,應通知該直轄市、縣(市)政府或鄉(鎮、市)公所。

English translation for reference only; the Chinese text prevails. Not legal advice.